Hereโs our latest Site Services project completed for a UK electric utility. Following a site survey, the team confirmed SF6 leaks on all phases of the asset, which required immediate repair and preventative maintenance. The project was for x6 flange repairs; x3 upper flange and x3 lower cover plate with sensor. All repairs were carried out under live conditions and full pressure. From surface preparations; to soft shell mounting and reinforcement; through to hard shell, resin application, final seal and post repair testing – our expert engineers followed proven and rigorous EMT protocols using trusted and reliable EMT technologies and solutions, to ensure compliance at every stage of the project.